S.D. Admin. R. 20:10:36:12

Current through Register Vol. 51, page 67, December 16, 2024
Section 20:10:36:12 - Site control documentation

Documentation of site control must be available. If the applicant is not currently a customer of the public utility, site control documentation shall be provided with the application. Site control may be demonstrated through ownership of, a leasehold interest in, or an option or other right to develop a site for the purpose of constructing the small generator facility. Site control may be documented by a property tax bill, deed, a lease agreement, or other legally binding contract.

S.D. Admin. R. 20:10:36:12

35 SDR 305, effective 7/1/2009.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.