The rules in this chapter govern the interconnection of small generator facilities in South Dakota with an electric nameplate capacity of ten megawatts or less to the electric distribution system of a public utility. The rules do not apply to small generator facilities subject to the interconnection requirements of FERC or a regional transmission organization. If a generation facility has an electric nameplate capacity of more than ten megawatts that may be subject to the commission's interconnection jurisdiction, this chapter may be used as the basis for the interconnection process.
S.D. Admin. R. 20:10:36:01
General Authority: SDCL 49-34A-27, 49-34A-93.
Law Implemented: SDCL 49-34A-27, 49-34A-93.