S.D. Admin. R. 20:10:28:56

Current through Register Vol. 51, page 67, December 16, 2024
Section 20:10:28:56 - Assignment of cost of other cable plant

In view of the small amounts involved, the cost of all protected terminals and gas pressure contractor terminals in the toll cable subaccount is assigned to the applicable interexchange cable and wire facilities categories. The cost of all other terminals in the exchange and toll cable subaccounts is assigned to exchange cable and wire facilities.

S.D. Admin. R. 20:10:28:56

19 SDR 111, effective 1/31/1993.

General Authority: SDCL 49-1-11, 49-31-5, 49-31-18.

Law Implemented: SDCL 49-31-18.

Assignment of cable and wire facilities to categories, 47 C.F.R. § 36.153(a) (1991).