S.D. Admin. R. 12:44:05:25

Current through Register Vol. 51, page 67, December 16, 2024
Section 12:44:05:25 - Contents of bulk commercial fertilizer storage facility permit application

A bulk commercial fertilizer storage facility permit application must include the following:

(1) Name, address, and telephone number of the following:
(a) The firm applying for a permit;
(b) The firm that will operate the facility; and
(c) The firm that will construct, install, or modify the site, if known;
(2) Type of facility (new, existing, or altered);
(3) Location of the facility (county, city, and township);
(4) Legal description of the facility location;
(5) Size of the lot owned or leased;
(6) Nature of the terrain (such as level area, steep slope);
(7) Type of storage containers (such as steel, poly, wood);
(8) Number of containers, their dimensions, and the capacity of each storage container;
(9) Copies of required local permits;
(10) Soil and groundwater conditions (general soil type at the site, such as clay, gravel, sand, or loam, and the type, depth, and proximity of wells on or near the site);
(11) Surface water (approximate distance to and identity of any nearby lake, stream, drainage ditch, or storm drain into which liquid could flow);
(12) Two scale drawings of plans and specifications for the facility, including other storage containers and buildings;
(13) Two copies of the plumbing diagram for the facility showing location and type of pumps and valves used to control all transferring;
(14) If a synthetic liner is used, a copy of the manufacturer's letter of compatibility and his written proof of certification of those qualified to install the liner;
(15) Signature, date of signature, and title of the person certifying information on the application; and
(16) Date of review by the secretary.

S.D. Admin. R. 12:44:05:25

15 SDR 194, effective 7/1/1989.

General Authority: SDCL 38-19-36, 38-19-36.1, 38-19-36.2.

Law Implemented: SDCL 38-19-36.2.