Section 12:05:07:05 - Truck approach at point of loading

The truck approach at the point of loading shall be graded and surfaced to prevent the pooling of water and to effectively protect the milk conducting hose from contamination. The area shall be provided with a concrete slab not less than four feet by eight feet centrally located adjacent to and below the port opening. The truck approach may not be located in a yard, walkway, or holding area where cattle can congregate.

S.D. Admin. R. 12:05:07:05

SL 1975, ch 16, § 1; 12 SDR 128, 12 SDR 154, effective 7/1/1986; 25 SDR 85, effective 12/20/1998; 28 SDR 177, effective 6/27/2002.

General Authority: SDCL 39-6-9.

Law Implemented: SDCL 39-6-9(9).