S.D. Admin. R. 10:09:03:02

Current through Register Vol. 51, page 67, December 16, 2024
Section 10:09:03:02 - Procedures for granting waivers

An agency may request a waiver by submitting a written request to the OSE prior to the construction documents phase of the project. OSE will provide a written response to the waiver request within 30 days of receipt. The written waiver request must include:

(1) Justification why a high performance building standard cannot be met; and
(2) Steps the owner will take to meet as many energy points as possible under the rating system; and
(3) If the request is based on the inability to recoup costs in 15 years, the calculations as defined in § 10:09:04:01; or
(4) If the square footage of the renovation project is less than fifty percent of the total square footage of the building being renovated, a three year building use plan.

S.D. Admin. R. 10:09:03:02

34 SDR 323, effective 7/3/2008.

General Authority: SDCL 5-14-38.

Law Implemented: SDCL 5-14-38.