Current through Register Vol. 48, No. 11, November 22, 2024
Section 61-91.1700.1704 - Submission of Plans and SpecificationsA. Plans and specifications shall be submitted to the Department for review and approval for new construction, additions or alterations to existing buildings, replacement of major equipment, buildings being licensed for the first time, buildings changing license type, and for facilities increasing occupant load or licensed capacity. Final plans and specifications shall be prepared by an architect and/or engineer registered in South Carolina and shall bear their seals and signatures. Architectural plans shall also bear the seal of a South Carolina registered architectural corporation. Unless directed otherwise by the Department, submit plans at the schematic, design development, and final stages. All plans shall be drawn to scale with the title, stage of submission and date shown thereon. Any construction changes from the approved documents shall be approved by the Department. Construction work shall not commence until a plan approval has been received from the Department. During construction the owner shall employ a registered architect and/or engineer for observation and inspections. Upon approval of the Department, construction administration may be performed by an entity other than the architect. The Department shall conduct periodic inspections throughout each project.B. Plans and specifications shall be submitted to the Department for review and approval for projects that have an effect on:1. The function of a space;2. The accessibility to or of an area;3. The structural integrity of the facility;4. The active and/or passive fire safety systems (including kitchen equipment such as exhaust hoods or equipment required to be under an exhaust hood);7. Ceiling system assemblies;9. Life safety systems; or10. That increases the occupant load or licensed capacity of the facility.C. All subsequent addenda, change orders, field orders, and documents altering the Department review must be submitted. Any substantial deviation from the accepted documents shall require written notification, review and re-approval from the Department.D. Cosmetic changes utilizing paint, wall covering, floor covering, etc., that are required to have a flame-spread rating or other safety criteria shall be documented with copies of the documentation and certifications kept on file at the facility and made available to the Department.E. Any construction work which violates codes or standards will be required to be brought into compliance. All projects shall obtain all required permits from the locality having jurisdiction. Construction without proper permitting shall not be inspected by Department.S.C. Code Regs. § 61-91.1700.1704
Amended by State Register Volume 39, Issue No. 06, eff. 6/26/2015; State Register Volume 48, Issue No. 06, eff. 6/28/2024.