S.C. Code Regs. § § 61-119.G.3

Current through Register Vol. 48, No. 11, November 22, 2024
Section 61-119.G.3 - Reconsideration of Nonconsumptive Use

If, after twenty-four (24) months of operation, a nonconsumptive permittee is shown not to meet the criteria of a non-consumptive user, the original permit application will be reevaluated. For an existing surface water withdrawer, a permit will be issued under section D of this regulation. For a non-consumptive use permit issued under section E of this regulation, a full review under section E will be conducted and an appropriately conditioned permit issued if the project is found to be reasonable under the Act.

S.C. Code Regs. § 61-119.G.3