Section 473.13 - Payment procedures

Unless otherwise specified by the Department, the following general procedures are to be used for funds from an aviation development grant:

(1) Prior to disbursement of funds, the Department reserves the right to conduct site inspections and test, or to review and audit records or accounts to validate, to the satisfaction of the Department, that disbursement of funds is warranted.
(2) A sponsor, having received payment or partial payment or reimbursement under an aviation development grant, shall make payments, within 30 calendar days from receipt of funds, to vendors and contractors for services and materials properly invoiced under the applicable project.
(3) A sponsor shall forward requests for payment to the Department on the forms provided. A request must include submission of actual cost documentation, consisting of approved contract estimates of work-in-place, approved invoices or other evidence of incurred costs, satisfactory to the Department. The final 10% of the total payment may not be paid by the sponsor until final inspection and approval of the project by the Department.
(4) Payment requests shall be limited to monthly submissions. The Bureau may request additional submissions to facilitate the end of year and grant closeout requirements.