28 Pa. Code § 153.4

Current through Register Vol. 54, No. 49, December 7, 2024
Section 153.4 - Approval of plans

For practical reasons, construction drawings should not be submitted for final approval to the Division of Safety Inspection until a Certificate of Need has been obtained where necessary. Final approval of construction drawings by the Division of Safety Inspection is not to be construed as a Certificate of Need approval.

28 Pa. Code § 153.4

The provisions of this § 153.4 adopted December 3, 1982, effective 12/4/1982, 12 Pa.B. 4129.

The provisions of this § 153.4 issued under section 2102(g) of The Administrative Code of 1929 (71 P. S. § 532(g)); and section 803 of the Health Care Facilities Act (35 P. S. § 448.803).