In addition to the requirements incorporated by reference, an owner or operator shall submit a schedule for construction of a hazardous waste management facility to the Department for approval. At a minimum, the schedule shall provide for inspection and approval by the Department of each phase of construction.
25 Pa. Code § 264a.15