Current through Register Vol. 54, No.43, October 26, 2024
Section 236.103 - Siting plan(a) The applicant shall submit a siting plan to the Department for approval. The siting plan shall meet the requirements of this subchapter and the act and follow the siting process discussed in the applicant's proposal. A quality assurance/quality control plan, which will be implemented throughout site screening and characterization, shall be submitted as part of the siting plan. Siting activities cannot begin until approval of the siting plan has been granted by the Department.(b) The Department will utilize its oversight role to ensure that the applicant is implementing the approved siting plan throughout the site screening and site characterization period. This section cited in 25 Pa. Code § 236.104 (relating to siting process); and 25 Pa. Code § 236.206 (relating to program plans).