Section 105.109 - As-built plans

Within 90 days after the final inspection or completion of the work, if the final inspection is waived by the Department, the permittee or owner shall file with the Department "as built" plans for the project, indicating revisions from the original plans and specifications.

25 Pa. Code § 105.109

The provisions of this §105.109 adopted January 7, 2011, effective 1/8/2011, 41 Pa.B. 219.

The provisions of this §105.109 issued under section 5 of the Dam Safety and Encroachments Act (32 P. S. § 693.5).

This section cited in 25 Pa. Code § 105.88 (relating to dam permit issuance).