25 Pa. Code § 105.61

Current through Register Vol. 54, No. 36, September 7, 2024
Section 105.61 - Procedures for investigations

The Department may, if it finds there is reasonable cause to suspect the existence of conditions adversely affecting the safety of a dam, water obstruction or encroachment, order the owner to conduct investigations, studies, tests and analyses that may be required to properly evaluate the safety of the structure. The investigations, studies, tests and analyses shall be accomplished under the supervision of a registered professional engineer, experienced in the design, construction, operation and maintenance of the facilities and approved by the Department, and shall be accomplished in accordance with methods the Department may prescribe. Failure to conduct the ordered investigations, studies, tests and analyses and provide the investigation results of the activities to the Department on request will constitute adequate grounds for revocation or suspension of a permit.

25 Pa. Code § 105.61

The provisions of this §105.61 adopted September 10, 1971, effective 9/11/1971, 1 Pa.B. 1804; amended August 11, 1978, effective 8/28/1978, 8 Pa.B. 2229; amended September 26, 1980, effective 9/27/1980, 10 Pa.B. 3843; amended January 7, 2011, effective 1/8/2011, 41 Pa.B. 219.

The provisions of this §105.61 amended under section 5 of the Dam Safety and Encroachments Act (32 P. S. § 693.5).