Section 102.43 - Withholding permits

With the exception of local stormwater approvals or authorizations, a municipality or county may not issue a building or other permit or approval to those proposing or conducting earth disturbance activities requiring a Department permit until the Department or a conservation district has issued the E&S or individual NPDES Permit, or approved coverage under the general NPDES Permit for Stormwater Discharges Associated With Construction Activities under § 102.5 (relating to permit requirements).

25 Pa. Code § 102.43

The provisions of this §102.43 adopted September 29, 1972, effective 10/30/1972, 2 Pa.B. 1796; corrected February 17, 1995, effective 10/30/1972, 25 Pa.B. 613; amended December 30, 1999, effective 1/1/2000, 30 Pa.B. 111; amended August 20, 2010, effective 11/19/2010, 40 Pa.B. 4861.

The provisions of this §102.43 amended under sections 5 and 402 of The Clean Streams Law (35 P. S. §§ 691.5 and 691.402); sections 1917-A and 1920-A of The Administrative Code of 1929 (71 P. S. §§ 510-17 and 510-20); and section 11(2) of the Conservation District Law (3 P. S. § 859(2)).