Persons submitting permit applications under § 86.14(a) (relating to permit application filing deadlines), shall reapply for a permit within 2 months by submitting an initial application on forms available from the Department and shall thereafter submit a complete application, including proof of publication, in accordance with a schedule determined by the Department. Other applications submitted under § 86.14(b) shall be complete and include, at a minimum, the applicable information required under this chapter and:
25 Pa. Code § 86.16
This section cited in 25 Pa. Code § 86.12 (relating to continued operation under interim permits); and 25 Pa. Code § 88.381 (relating to general requirements).