A person who expects to conduct new noncoal mining activities shall file a complete application for a permit for noncoal mining activities a minimum of 180 days prior to the anticipated starting date of the activities or a shorter period of time as determined by the Department.
25 Pa. Code § 77.103
This section cited in 25 Pa. Code § 77.105 (relating to application contents).