Section 918-050-0160 - Statewide Fee Methodology for Phased Projects

A municipal plan review fee for a phased project is based on a minimum phasing fee, determined by the municipality, plus 10 percent of the total project building permit fee not to exceed $1,500 for each phase.

Or. Admin. Code § 918-050-0160

BCD 11-2002, f. 6-28-02, cert. ef. 7-1-02; BCD 31-2005, f. 12-30-05, cert. ef. 1-1-06; BCD 27-2008, f. ef.12-12-08, cert. ef. 1-1-09

Stat. Auth.: ORS 455.048 & 455.055

Stats. Implemented: ORS 455.046 & 455.055