Current through Register Vol. 63, No. 12, December 1, 2024
Section 918-460-0070 - Phased Project and Deferred Submittal FeesWhen requested to review and approve plans for phased construction or deferred plan submittals under the Oregon Structural Specialty Code, the following fees in addition to the applicable plan review and permit fees shall apply.
(1) Phased Projects. There shall be an application fee of $100 for each separate phase of the project. In addition, the plan review fee shall be increased in an amount equal to 10 percent of the building permit fee calculated according to OAR 918-460-0050 using the value of the particular phase of the project, not to exceed an additional $1,500 for each phase.(2) Deferred Submittals. The fee for processing and reviewing deferred plan submittals shall be an amount equal to 65 percent of the building permit fee calculated according to OAR 918-460-0050 using the value of the particular deferred portion or portions of the project. This fee is in addition to the project plan review fee based on total project value.Or. Admin. Code § 918-460-0070
BCD 26-2001, f. 12-28-01, cert. ef. 1-1-02Publications: Publications referenced are available from the agency.
Stat. Auth.: ORS 455.020
Stats. Implemented: ORS 455.020