Or. Admin. Code § 734-051-3010

Current through Register Vol. 63, No. 12, December 1, 2024
Section 734-051-3010 - Permit for Private Approach
(1) Applicability. This rule applies to applications for state highway approach permits for private approaches.
(2) Restricted Areas. The department shall not issue an approach permit to a freeway, a freeway ramp, or an expressway ramp, or an approach that would be aligned opposite a freeway or expressway ramp terminal.
(3) Rules in Effect. An application for an approach permit shall be subject to the rules in effect on the date the application was filed. The department shall use OAR 734, division 51, and ORS 374, and may use other applicable statutes or administrative rules to evaluate and act on an application.
(4) Approach Permit Approval Criteria. The department shall approve an application for an approach based upon a determination that it meets all of the following criteria:
(a) The department determines that a complete application has been submitted pursuant to OAR 734-051-3030;
(b) The department determines that the application is consistent with any applicable facility plans adopted by the Oregon Transportation Commission, including special transportation area plans, facility plans, corridor plans;
(c) Except where paragraphs (A) through (D) of this subsection apply, the department determines that the proposed approach meets the spacing, channelization and sight distance standards of OAR 734-051-4020, or the department approves a deviation from these standards under OAR 734-051-3050 which may include mitigation measures pursuant to OAR 734-051-3070;
(A) OAR 734-051-3020 applies to applications for change of use of a private approach.
(B) OAR 734-051-4020(5) applies to applications for properties with no alternate access.
(C) OAR 734-051-4040 applies to applications for temporary approaches.
(D) OAR 734-051-4050 applies to applications for special use approaches.
(d) The department determines that the approach does not create or contribute to a safety or highway operations concern, as identified in OAR 734-051-4020(3), or such concerns are sufficiently mitigated pursuant to OAR 734-051-3070.
(5) Cooperative Improvement Agreement. A written agreement between the applicant and the department may be required. The agreement will address transfer of ownership of the improvements to ODOT, work standards that must be followed, any maintenance responsibilities of the applicant, and other requirements that apply to the work. ODOT may withhold issuance of a Permit to Construct under 734-051-5020 or a Permit to Operate, Maintain, and Use an Approach under 734-051-5080 until the agreement is fully executed by all parties. ODOT will work with the applicant to identify the need and develop the provisions for the agreement early in the permitting process in order to avoid delays in obtaining permits.

Or. Admin. Code § 734-051-3010

HWD 16-2011(Temp), f. 12-22-11, cert. ef. 1-1-12 thru 6-29-12; HWD 8-2012, f. 6-27-12, cert. ef. 6-29-12; HWD 2-2014, f. 6-25-14, cert. ef. 6-30-14; HWD 7-2014, f. & cert. ef. 7-9-14

Stat. Auth.: ORS 184.616, 184.619, 374.310-374.314, 374.345 & 374.355

Stats. Implemented: ORS 374.300-374.360, §27, ch. 330, OL 2011