Current through Register Vol. 63, No. 10, October 1, 2024
Section 340-095-0090 - Financial Assurance Criteria(1) Financial Assurance Required. The owner or operator of a non-municipal land disposal site shall maintain a financial assurance plan with detailed written cost estimates of the amount of financial assurance that is necessary and shall provide evidence of financial assurance for the costs of: (a) Closure of the non-municipal land disposal site; (b) Post-closure maintenance of the non-municipal land disposal site; and (c) Any corrective action required by the Department to be taken at the non-municipal land disposal site, pursuant to OAR 340-095-0040(3). (2) Exemptions. The Department may exempt from the financial assurance requirements any non-municipal land disposal site including but not limited to construction and demolition waste sites, composting facilities and industrial waste sites: (a) Exemption criteria. To be eligible for this exemption, the applicant shall demonstrate to the satisfaction of the Department that the site meets all of the following criteria and that the site is likely to continue to meet all of these criteria until the site is closed in a manner approved by the Department: (A) The non-municipal land disposal site poses no significant threat of adverse impact on groundwater or surface water; (B) The non-municipal land disposal site poses no significant threat of adverse impact on public health or safety; (C) No system requiring active operation and maintenance is necessary for controlling or stopping discharges to the environment; (D) The area of the non-municipal land disposal site that has been used for waste disposal and has not yet been properly closed in a manner acceptable to the Department is less than and remains less than two acres or complies with a closure schedule approved by the Department. (b) In determining if the applicant has demonstrated that a non-municipal land disposal site meets the financial assurance exemption criteria, the Department will consider existing available information including, but not limited to, geology, soils, hydrology, waste type and volume, proximity to and uses of adjacent properties, history of site operation and construction, previous compliance inspection reports, existing monitoring data, the proposed method of closure and the information submitted by the applicant. The Department may request additional information if needed; (c) An exemption from the financial assurance requirement granted by the Department will remain valid only so long as the non-municipal land disposal site continues to meet the exemption criteria in subsection (2)(a) of this rule. If the site fails to continue to meet the exemption criteria, the Department may modify the permit to require financial assurance. (3) Schedule for provision of financial assurance: (a) For costs associated with the conceptual "worst-case" closure plan and the conceptual post-closure plan prepared pursuant to OAR 340-095-0060(1)(a)(A) and OAR 340-095-0065(1)(a), respectively: Evidence of the required financial assurance for closure and post-closure maintenance of the non-municipal land disposal site shall be provided on the following schedule: (A) For a new non-municipal land disposal site: no later than the time the solid waste permit is issued by the Department and prior to first receiving waste; or (B) For a non-municipal land disposal site operating under a solid waste permit on November 4, 1993: by April 9, 1997. (b) For costs associated with the Final Engineered Site Closure Plan and the Final Engineered Post-closure Plan prepared pursuant to OAR 340-095-0060(1)(a)(B) and OAR 340-095-0065(1)(b) respectively: Evidence of the required financial assurance for closure and post-closure maintenance of the land disposal site shall be provided at the same time those two Plans are due to the Department; (c) Evidence of financial assurance for corrective action shall be provided before beginning corrective action; (d) Continuous financial assurance shall be maintained for the facility until the permittee or other person owning or controlling the site is no longer required to demonstrate financial responsibility for closure, post-closure care or corrective action (if required). (4) Financial assurance plans. The financial assurance plan is a vehicle for determining the amount of financial assurance necessary and demonstrating that financial assurance is being provided. A financial assurance plan shall include but not be limited to the following, as applicable: (a) Cost Estimates. A detailed written estimate of the third-party costs in current dollars (as calculated using a discount rate equal to the current yield of a 5-year U.S. Treasury Note as published in the Federal Reserve's H.15 (519) Selected Interest Rates for the week in which the calculation is done), prepared by a Registered Professional Engineer, of: (A) Closing the non-municipal land disposal site; (B) Providing post-closure care, including installing, operating and maintaining any environmental control system required on the non-municipal land disposal site; (C) Performing required corrective action activities; and (D) Complying with any other requirement the Department may impose as a condition of issuing a closure permit, closing the site, maintaining a closed facility, or implementing corrective action. (b) The source of the cost estimates; (c) A detailed description of the form of the financial assurance and a copy of the financial assurance mechanism; (d) A method and schedule for providing for or accumulating any required amount of funds which may be necessary to meet the financial assurance requirement; (e) A proposal with provisions satisfactory to the Department for disposing of any excess moneys received or interest earned on moneys received for financial assurance, if applicable: (A) To the extent practicable and to the extent allowed by any franchise agreement, the applicant's provisions for disposing of the excess moneys received or interest earned on moneys shall provide for: (i) A reduction of the rates a person within the area served by the non-municipal land disposal site is charged for solid waste collection service as defined by ORS 459.005; or (ii) Enhancing present or future solid waste disposal facilities within the area from which the excess moneys were received. (B) If the non-municipal land disposal site is owned and operated by a private entity not regulated by a unit of local government, excess moneys and interest remaining in any financial assurance reserve shall be released to that business entity after post-closure care has been completed and the permittee is released from permit requirements by the Department. (f) The financial assurance plan shall contain adequate accounting procedures to insure that the permittee does not collect or set aside funds in excess of the amount specified in the financial assurance plan or any updates thereto or use the funds for any purpose other than required by paragraph (8)(a) of this rule; (g) The certification required by subsection (6)(c) of this rule; and (h) The annual updates required by subsection (6)(d) of this rule. (5) Amount of Financial Assurance Required. The amount of financial assurance required shall be established as follows: (a) Closure. Detailed cost estimates for closure shall be based on the conceptual "worst-case" closure plan or the final Engineered Site Closure Plan, as applicable. Cost estimates for the Final Engineered Site Closure plan shall take into consideration at least the following: (A) Amount and type of solid waste deposited in the site; (B) Amount and type of buffer from adjacent land and from drinking water sources; (C) Amount, type, availability and cost of required cover; (D) Seeding, grading, erosion control and surface water diversion required; (E) Planned future use of the disposal site property; (F) The portion of the site property closed before final closure of the entire site; and (G) Any other conditions imposed on the permit relating to closure of the site. (b) Post-closure care. Detailed cost estimates for post-closure care shall be based on the conceptual post-closure plan or the Final Engineered Post-closure Plan, as applicable. Cost estimates for the Final Engineered Post-closure Plan shall also take into consideration at least the following: (A) Type, duration of use, initial cost and maintenance cost of any active system necessary for controlling or stopping discharges; and (B) Any other conditions imposed on the permit relating to post-closure care of the site. (c) Corrective action. Estimated total costs of required corrective action activities for the entire corrective action period, as described in a corrective action report pursuant to requirements of OAR 340-095-0040(3); (d) If a permittee is responsible for providing financial assurance for closure, post-closure care and/or corrective action activities at more than one non-municipal land disposal site, the amount of financial assurance required is equal to the sum of all cost estimates for each activity at each facility. (6) How Financial Assurance Is to Be Provided and Updated: (a) The permittee shall submit to the Department a copy of the first financial assurance mechanism prepared in association with a conceptual "worst-case" closure plan, a Final Engineered Site Closure Plan, a conceptual post-closure plan, a Final Engineered Post-closure Plan, and a corrective action report; (b) The permittee shall also place a copy of the applicable financial assurance plan(s) in the facility operations office or another location approved by the Department on the schedule specified in Section (3) of this rule; (c) The permittee shall certify to the Director at the time a financial assurance plan is placed in the facility operations office or other approved location that the financial assurance mechanism meets all state requirements. This date becomes the "annual review date" of the provision of financial assurance, unless a corporate guarantee is used, in which case the annual review date is 90 days after the end of the corporation's fiscal year; (d) Annual update. The permittee shall annually review and update the financial assurance during the operating life and post-closure care period, or until the corrective action is completed, as applicable: (A) The annual review shall include: (i) An adjustment to the cost estimate(s) for inflation and in the discount rate as specified in subsection (4)(a) of this rule; (ii) A review of the closure, post-closure and corrective action (if required) plans and facility conditions to assess whether any changes have occurred which would increase or decrease the estimated maximum costs of closure, post-closure care or corrective action since the previous review; (iii) If a trust fund or other pay-in financial mechanism is being used, an accounting of amounts deposited and expenses drawn from the fund, as well as its current balance. (B) The financial assurance mechanism(s) shall be increased or may be reduced to take into consideration any adjustments in cost estimates identified in the annual review; (C) The annual update shall consist of a certification from the permittee submitted to the Department and placed in the facility operations office or other approved location. The certification shall state that the financial assurance plans(s) and financial assurance mechanism(s) have been reviewed, updated and found adequate, and that the updated documents have been placed at the facility operations office or other approved location. The annual update shall be no later than: (i) The facility's annual review date; or (ii) For a facility operating under a closure permit, by the date specified in OAR 340-095-0050(3). (7) Department Review of Financial Assurance and Third-Party Certification: (a) The Department may at any time select a permittee to submit financial assurance plan(s) and financial assurance mechanism(s) for Department review. Selection for review will not occur more frequently than once every five years, unless the Department has reasonable cause for more frequent selection. The Department may, however, review such plans and mechanisms in conjunction with a site inspection at any time; (b) A permittee who wants to provide "alternative financial assurance" pursuant to OAR 340-095-0095(6)(g) shall submit its financial assurance plan and proposed financial assurance mechanism for Department review and approval on the schedule specified in section (3) of this rule. The submittal shall include certification from a qualified third party that the financial assurance mechanism meets all state requirements for financial assurance, and is reasonably designed to provide the required amount of financial assurance. The third-party certification shall be submitted in a format acceptable to the Department; (c) The Department will review the financial assurance and the third-party certification, if applicable, for compliance with state laws. (8) Accumulation of any financial assurance funds: (a) The financial assurance mechanisms for closure, post-closure care and corrective action shall ensure the funds will be available in a timely fashion when needed. The permittee shall pay moneys into a trust fund in the amount and at the frequency specified in the financial assurance plan or obtain other financial assurance mechanisms as specified in the financial assurance plan, on the schedule specified in section (3) of this rule: (A) Closure. The total amount of financial assurance required for closure shall be available in the form specified in the financial assurance plan or any updates thereto, whenever final closure of a non-municipal land disposal site unit is scheduled to occur in the conceptual "worst case" closure plan or in the Final Engineered Site Closure Plan; (B) Post-closure care. The total amount of financial assurance required for post-closure care shall be available in the form specified in the financial assurance plan or any updates thereto, whenever post-closure care is scheduled to begin for a non-municipal land disposal site unit in the conceptual post-closure plan or in the Final Engineered Post-closure Plan; (C) Corrective action. The total amount of financial assurance required for corrective action shall be available in the form specified in the financial assurance plan or any updates thereto on the schedule specified in the corrective action selected pursuant to OAR 340 Division 40. (b) The permittee is subject to audit by the Department (or Secretary of State) and shall allow the Department access to all records during normal business hours for the purpose of determining compliance with this rule and OAR 340-095-0095; (c) If the Department determines that the permittee did not set aside the required amount of funds for financial assurance in the form and at the frequency required by the applicable financial assurance plan, or if the Department determines that the financial assurance funds were used for any purpose other than as required in section (1) of this rule, the permittee shall, within 30 days after notification by the Department, deposit a sufficient amount of financial assurance in the form required by the applicable financial assurance plan along with an additional amount of financial assurance equal to the amount of interest that would have been earned, had the required amount of financial assurance been deposited on time or had it not been withdrawn for unauthorized use; (d) If financial assurance is provided under OAR 340-095-0095(6)(a), (b) or (g), upon successful closure and release from permit requirements by the Department, any excess money in the financial assurance account must be used in a manner consistent with subsection (4)(e) of this rule.Or. Admin. Code § 340-095-0090
DEQ 2-1984, f. & ef. 1-16-84; DEQ 5-1993, f. & cert. ef. 3-10-93, Renumbered from 340-061-0034; DEQ 10-1994, f. & cert. ef. 5-4-94; DEQ 2-1995, f. & cert. ef. 1-10-95; DEQ 8-1995(Temp), f. & cert. ef. 4-25-95; DEQ 23-1995(Temp), f. & cert. ef. 10-10-95; DEQ 27-1998, f. & cert. ef. 11-13-98; DEQ 7-2013, f. & cert. ef. 8-29-13 Publications referenced are available from the agency.
Stat. Auth.: ORS 459.045, 459A.025 & 468.020
Stats. Implemented: ORS 459.248, 459.272 & 459.273