Following receipt of construction bids, the agency shall submit three copies each of the following documents to the Department for review and approval of contract award: tabulation of all bids received; engineer's analysis of bids; engineer's recommendations; low bidder's proposal; publisher's affidavits of advertising; and a current project cost estimate summary including an estimate of funds available for the project.
Or. Admin. Code § 340-082-0045
Stat. Auth.:ORS 468
Stats. Implemented:ORS 468.195 -ORS 468.272