Or. Admin. Code § 340-175-0050

Current through Register Vol. 63, No. 12, December 1, 2024
Section 340-175-0050 - Additional Information Required on the Financial Assistance Application

In addition to the requirements of OAR 340-172-0040, the financial assistance application shall include:

(1) Where the UST project work is partially or fully completed:
(a) A description of the completed UST project work including the date the UST was placed into service;
(b) Cost of completed UST project work; and
(c) A description of all UST project work still to be done to meet new UST standards, including estimated cost and schedule of work.
(2) A signed agreement meeting the requirements of OAR 340-175-0055.

Or. Admin. Code § 340-175-0050

DEQ 29-1991(Temp), f. 12-18-91, cert. ef. 12-20-91; DEQ 14-1992, f. & cert. ef. 6-11-92; DEQ 8-1994, f. & cert. ef. 3-22-94

Stat. Auth.: OL 1993, Ch. 661

Stats. Implemented:OL 1991, Ch. 863, Sec. 7