Current through Register Vol. 63, No. 12, December 1, 2024
Section 330-025-0015 - Resource Plan Submission Requirement(1) On or before July 1, 1982, and on or before every April 1 of even numbered years thereafter, each utility shall submit to the Director a resource plan. This plan shall forecast and describe how the utility will meet demand on its Oregon system (or the systems of its members) over a fifteen-year period as determined by EFSC's most recent biennial forecast of demand and supply. This plan will meet the utility forecast requirement contained in ORS 469.070(4) for those years that a resource plan is due.(2) Utilities do not have to submit a revised plan if and when EFSC revises its biennial forecast in the interim period between the development of consecutive biennial forecasts.Or. Admin. Code § 330-025-0015
DOE 4-1982, f. & ef. 3-12-82Stat. Auth.: ORS 469
Stats. Implemented: ORS 469.080