Within thirty (30) days of completion of a new dam or reservoir or enlargement or repair of a dam or reservoir, the owner shall give notice of completion and as soon thereafter as possible shall file supplementary drawings or descriptive matter showing or describing the dam or reservoir as actually constructed, including the following:
(1) A record of all grout holes and grouting;(2) A record of permanent location points and bench marks;(3) A record of tests of concrete soils, or other materials used in the construction of the dam or reservoir;(4) Any other items which may be of permanent value and have a hearing on the safety and performance of the dam or reservoir; and(5) For dams classified as high hazard-potential, a breach analysis report and map showing the breach inundation area utilizing the publication Hydrologic and Hydraulic Guidelines for Dams in Oklahoma, Oklahoma Water Resources Board, Dam Safety Program, August 2011.Okla. Admin. Code § 785:25-7-6
Amended at 30 Ok Reg 883, eff 6-13-13
Amended by Oklahoma Register, Volume 41, Issue 22, August 1, 2024, eff. 8/11/2024