Okla. Admin. Code § 260:65-27-11

Current through Vol. 42, No. 8, January 2, 2025
Section 260:65-27-11 - Risk minimization and performance
(a) The Risk Minimization and Performance Measurement phase begins upon award of the project contract. Risk includes anything that impacts project cost, quality or project schedule caused by the vendor, the State, unforeseen conditions or other parties. The Phase consists of, but is not limited to:
(b)Weekly Risk Report System (WRR). The WRR is a project requirement and tool the vendor must use to manage and document all risks that occur throughout a project. The WRR is a standardized format prescribed by the Director, which may include:
(1) all key contact information;
(2) project milestone schedule;
(3) risk sheet;
(4) modification/deviation tracking;
(5) risk management plan (RMP);
(6) any risks the Department may require the vendor to document that could impact the customer or the Department's satisfaction.
(7) performance measurements
(c) The vendor shall submit a risk report for the project/service weekly throughout their contract, or as otherwise required by the Director.

Okla. Admin. Code § 260:65-27-11

Adopted by Oklahoma Register, Volume 31, Issue 24, September 2, 2014, eff. 9/12/2014
Amended by Oklahoma Register, Volume 40, Issue 24, September 1, 2023, eff. 9/11/2023