Section 260:65-25-4 - Determination of a need for pre-design services

Upon review of the notice of intent submitted by the agency, the Director will consult with the agency and determine the specific project planning requirements. The Director shall determine a need for pre-design services based on the following factors:

(1) Building type;
(2) Project complexity;
(3) Project schedule;
(4) Funding sources or funding constraints; and,
(5) Other factors unique to the project.

Okla. Admin. Code § 260:65-25-4

Adopted by Oklahoma Register, Volume 31, Issue 24, September 2, 2014, eff. 9/12/2014
Amended by Oklahoma Register, Volume 40, Issue 24, September 1, 2023, eff. 9/11/2023