Current through Vol. 42, No. 4, November 1, 2024
Section 165:40-5-30 - Reactive power(a) Producer will generate sufficient reactive power reasonably necessary to meet requirements of the service agreement.(b) Cooperative/utility may request new capacity and/or reactive power rating for facility if it is reasonably apparent they are no longer correct.(c) To the extent that producer's facility fails to achieve a power factor of at least eighty-five (85%) percent, producer shall pay for var support under the appropriate tariff.Okla. Admin. Code § 165:40-5-30