Okla. Admin. Code § 165:40-5-21

Current through Vol. 42, No. 4, November 1, 2024
Section 165:40-5-21 - Change of facility requirements
(a) The cooperative/utility shall have the right to change transformers and interconnection voltage when necessary.
(b) The producer shall make or bear the cost of changes in interconnection, protection, and reinforcement facilities necessary to meet changing system conditions and requirements.

Okla. Admin. Code § 165:40-5-21