Okla. Admin. Code § 165:35-45-4

Current through Vol. 42, No. 7, December 16, 2024
Section 165:35-45-4 - Notification of intent to build a wind energy facility and other notices
(a) Within six (6) months of the initial filing with the FAA, the owner of a wind energy facility shall electronically submit to the PUD Director all initial 7460-1 forms for all individual wind turbines or any other individual structure that requires a FAA Form 7460-1 that is part of a wind energy facility, an attestation of compliance with the provisions of 17 O.S. § 160.20(A), and a map of the project boundary. Within thirty (30) days of the initial filing with the FAA, the owner of a wind energy facility shall submit copies of all initial 7460-1 forms for individual wind turbines and other individual structures that require a 7460-1 that are part of a wind energy facility to the Aeronautics Commission.
(b) Prior to the construction or the transfer of ownership of a wind energy facility, the owner shall furnish to the Public Utility Division a certified copy by the issuing financial institution, evidence of financial security consistent with 17 O.S. § 160.15(A).
(c) Evidence of financial security will be satisfied when it ensures the financial security will be held for decommissioning of the wind facility and will allow the Corporation Commission to access the funds for the purpose of decommissioning pursuant to 17 O.S. § 160.14.
(d) PUD shall provide the owner of a wind energy facility with affirmation of submission of the notification of intent to build by either providing proof of receipt stamp or confirmation of receipt if submission is made electronically.
(e) The owner of the wind energy facility shall send copies of the notification with the board of county commissioners of every county in which all or a portion of the wind energy facility is to be located within twenty-four (24) hours of submission with the Commission. If all or a portion of the wind energy facility is to be located within the incorporated area of a municipality, copies of the notification shall also be sent to the governing body of the municipality within twenty-four (24) hours of submission with the Commission.
(f) Within six (6) months of submitting the notification with the Commission as provided for in subsection (a) of this section, the owner of the wind energy facility shall cause a copy of the notification to be published in a newspaper of general circulation in the county or counties in which all or a portion of the wind energy facility is to be located. Proof of publication shall be submitted to the PUD Director.
(g) Within sixty (60) calendar days of publishing the notification in a newspaper as provided for in subsection (f) of this section, the owner of the wind energy facility shall hold a public meeting. Notice of the public meeting shall be published in a newspaper of general circulation and submitted to the board of county commissioners in the county or counties in which all or a portion of the wind energy facility is to be located. The notice shall contain the place, date and time of the public meeting. Proof of publication of the notice shall be submitted to the PUD Director. The public meeting shall be held in one of the counties in which all or a portion of the wind energy facility is to be located.
(h) If the owner of a wind energy facility is required to file subsequent 7460-1 forms with the FAA due to changing locations or heights of individual structures from the locations or heights originally proposed in the initial 7460-1 forms submitted to the Oklahoma Aeronautics Commission, the owner shall, within ten (10) calendar days of filing with the FAA, submit such subsequent 7460-1 forms to the Corporation Commission and Aeronautics Commission. A wind energy facility owner shall not be required to start the notification processes over unless the subsequent 7460-1 forms expand the project beyond its original project boundary submitted to the Corporation Commission.
(i) The owner of a wind energy facility shall not commence construction on the facility until the notification and public meeting requirements of this section have been met. If an owner of a wind energy facility fails to submit the information as required in this section, the owner shall be subject to an administrative penalty from the Commission not to exceed One Thousand Five Hundred Dollars ($1,500) per day, per violation following hearing and issuance of a final order of the Commission.
(j) No individual wind turbine or any other individual structure that requires a FAA 7460-1 form that is part of a wind energy facility may be constructed or expanded unless there is an active Determination of No Hazard from the FAA and adverse impacts to the United States Department of Defense, pursuant to Title 32 of the Code of Federal Regulations, Section 211.6, have been resolved as evidenced by documentation from the Clearinghouse for the individual wind turbine or other individual structure. The Mission Compatibility Certification Letter or successor form may serve as such evidence of adverse impacts being resolved with the Department of Defense or successor agency. Determinations of No Hazard and documentation of the resolution of adverse impacts to the Department of Defense shall be submitted by the owner of a wind energy facility to the Corporation Commission and the Aeronautics Commission.
(k) If an owner of a wind energy facility fails to submit an active Determination of No Hazard and documentation that adverse impacts to the Department of Defense have been resolved by the Clearinghouse for the individual turbine or other individual structure prior to the start of construction, the owner shall be subject to an administrative penalty not to exceed One Thousand Five Hundred Dollars ($1,500.00) per day, per violation from the Corporation Commission.
(l) All notices, notifications, Determinations of No Hazard, and proof of compliance with all provisions of the Oklahoma Wind Energy Development Act, shall be retained by the wind energy developer, for a period of three (3) years after commercial operation date; and, upon reasonable request, PUD may inspect these documents to ensure compliance.
(m) The owner of a wind energy facility shall electronically provide a notice to the PUD Director indicating that it has commenced the 60-day notice as required by 17 O.S. § 160.21(F). Such notice shall be sent to the PUD Director prior to commencement of construction of the wind energy facility. The notice to the PUD Director shall also include an affirmation that all required notices and notifications have been properly provided, and a list of the recipients of all required notices and notifications shall be retained by the wind energy developer and made available to PUD upon reasonable request.
(n) All submissions shall be submitted electronically to PUD, unless prior approval is granted by the PUD Director.

Okla. Admin. Code § 165:35-45-4

Adopted by Oklahome Register, Volume 33, Issue 23, August 15, 2016, eff. 8/25/2016
Amended by Oklahoma Register, Volume 36, Issue 21, July 15, 2019, eff. 7/25/2019
Amended by Oklahoma Register, Volume 37, Issue 24, September 1, 2020, eff. 9/15/2020
Amended by Oklahoma Register, Volume 41, Issue 23, August 15, 2024, eff. 10/1/2024