Current through Vol. 42, No. 7, December 16, 2024
Section 165:25-1-60 - Walkthrough inspections and records(a) Owners and operators must conduct walkthrough inspections according to the requirements in 40 CFR 280.36. Owners and operators of underground storage tank systems must maintain a record of 30-day and annual walkthrough inspections according to EPA requirements with the first inspection due by October 13, 2018. (1) Every 30 days all spill prevention equipment and release detection equipment must be inspected (except spill prevention equipment at UST systems receiving deliveries at intervals greater than 30 days may be checked prior to delivery). Containment sumps and any hand-held release detection equipment, such as tank gauge sticks, must be inspected annually. (2) Records should include a list of each area checked, whether each area checked was acceptable or needed action taken, a description of any actions taken to correct issues, and delivery records if spill prevention equipment is checked less frequently. (b) In addition, airport hydrant systems must meet the additional walkthrough inspection requirement in 40 CFR 280.252(c). (c) All walkthrough inspection records must be on Commission forms and maintained on site for three (3) years. Okla. Admin. Code § 165:25-1-60
Adopted by Oklahome Register, Volume 33, Issue 23, August 15, 2016, eff. 8/25/2016Amended by Oklahoma Register, Volume 34, Issue 24, September 1, 2017, eff. 9/11/2017Amended by Oklahoma Register, Volume 36, Issue 21, July 15, 2019, eff. 8/1/2019