Prior to including incentive/disincentive provisions in a contract the director shall calculate on a per project basis a daily or fraction thereof incentive/disincentive amount considering: construction engineering inspection costs, departmental traffic control costs and maintenance, detour and road user costs. The incentive rate may equal the disincentive rate.