Bin Classification Table for Systems
For systems that are: | With a Crypotosporidium bin 1 concentration of: | The bin classification is: |
... required to monitor for [Cryptosporidium] as specified in paragraphs (A) to (H) of rule 3745-81-65 of the Administrative Code. | Cryptosporidium < 0.075 oocyst/L | Bin 1. |
0.075 oocysts/L < =Cryptosporidium, < 1.0 oocysts/L | Bin 2. | |
1.0 oocysts/L < = Cryptosporidium, < 3.0 oocysts/L | Bin 3. | |
Cryptosporidium > = 3.0 oocysts/L | Bin 4. | |
... serving less than 10,000 people and NOT required to monitor for Cryptosporidium under paragraph (A)(4) of rule 3745-81-65 of the Adminstrative Code. | Not applicable | Bin 1. |
1 Based on calculations in paragraph (A) or (C) of this rule, as applicable.
Systems shall report their initial bin classification to the director for approval no later than six months after the system is required to complete initial source water monitoring based on the schedule in paragraph (C) of rule 3745-81-65 of the Administrative Code. The bin classification report to the director shall include a summary of source water monitoring data and the calculation procedure used to determine bin classification.
For systems serving less than one hundred thousand within twelve months after the system is required to complete initial source water monitoring, the system shall submit a general plan to the director indicating the system's plan for complying with any additional Cryptosporidium inactivation or removal requirements. Systems serving at least one hundred thousand people shall submit a general plan by March 1, 2010. The general plan shall include at a minimum, a description of each toolbox option which may be used, and a schedule for submitting any required detail plans or protocols/pilot study results for the proposed toolbox option. The general plan shall be prepared and submitted by a professional engineer.
Within six months of receiving the director's approval of the bin classification, the system shall submit a general plan to the director indicating the system's plan for complying with any additional Cryptosporidium inactivation or removal requirements. The general plan shall include at a minimum, a description of each toolbox option which may be used, and a schedule for submitting any required detail plans or protocols/pilot study results for the proposed toolbox option.
Additional Cryptosporidium treatment requirements based on bin classification.
If the system bin classification is... | And the system uses the following filtration treatment in full compliance with rules 3745-81-71 to 3745-81-76 of the Administrative Code (as applicable), then the additional Cryptosporidium treatment requirements are... | |||
Conventional filtration treatment (including softening) | Direct filtration | Slow sand or diatmaceous earth filtration | Alternative filtration technologies | |
Bin 1 | No additional treatment | No additional treatment | No additional treatment | No additional treatment |
Bin 2 | 1-log treatment | 1.5 -log treatment | 1-log treatment | As determined by the director such that the total Cryptosporidium removal and inactivation is at least 4.0 -log. |
Bin 3 | 2-log treatment | 2.5 -log treatment | 2-log treatment | As determined by the director such that the total Cryptosporidium removal and inactivation is at least 5.0 -log. |
Bin 4 | 2.5 - log treatment | 3-log treatment | 2.5 -log treatment | As determined by the director such that the total Cryptosporidium removal and inactivation is at least 5.5 -log. |
Cryptosporidium Treatment Compliance Dates Table
Systems that serve: | Shall comply with Cryptosporidium treatment requirements no later than... * |
(1) At least 100,000 people. | (1) April 1, 2012 |
(2) From 50,000 to 99,999 people. | (2) October 1, 2012 |
(3) From 10,000 to 49,999 people. | (3) October 1, 2013 |
(4) Fewer than 10,000. | (4) October 1, 2014 |
* Systems with a bin classification of Bin 3 or Bin 4 shall have an additional two years for complying with the treatment requirement if capital improvements will be made. The director may allow up to an additional two years for complying with the treatment requirement for systems in Bin 2 if capital improvements will be made. |
Ohio Admin. Code 3745-81-67
Five Year Review (FYR) Dates: 1/22/2020 and 03/01/2027
Promulgated Under: 119.03
Statutory Authority: 6109.04
Rule Amplifies: 6109.03, 6109.04
Prior Effective Dates: 01/08/2010