[Comment: In the case of any reference to any building, the measurement shall be taken from the outside wall of the building. In the case of any reference to a treatment works or a component of the treatment works or a pump station, the measurement shall be taken from the closest point on the perimeter of the treatment works, the component of the treatment works, or the pump station. In the case of any reference to an earthen lagoon or storage facility, the measurement shall be taken from the outer bank or the toe of the earthen impoundment.]
Table A-1: Isolation distance requirements.
Component of disposal system | Minimum isolation distance required from an occupied building | Minimum isolation distance required from surface waters of the state |
Earthen impoundment that contains sewage or treated sewage | Three hundred feet | Three hundred feet |
Earthen impoundment that contains industrial waste, other than industrial waste generated from the recovery of any natural resource, such as a quarry mining operation | Three hundred feet | Three hundred feet |
Sewage sludge drying bed | Three hundred feet | Three hundred feet |
Covered sand filter | One hundred fifty feet | Three hundred feet |
Housing or building enclosure for extended aeration treatment works | One hundred fifty feet | One hundred fifty feet |
Pump station | Fifty feet | Thirty-five feet |
Any other component of a treatment works, not including (1) a disposal field, (2) a land application area or (3) a wet weather management facility for treating combined sewer overflows or sanitary sewer overflows | Two hundred feet | Three hundred feet |
[Comment: A high density development includes a residential development of homes or condominiums, a commercial development, such as a shopping mall, or a business park development.]
[Comment: Potential impacts to neighboring buildings could include odors or the probability that either an overflow or a breach could inundate neighboring buildings, causing harm to life, health or property. Applicants proposing to construct above ground impoundments should also contact the Ohio department of natural resources division of dam safety. The web page is: http://water.ohiodnr.gov/safety/dam-safety. ]
Ohio Admin. Code 3745-42-08
Five Year Review (FYR) Dates: 10/11/2017 and 02/23/2023
Promulgated Under: 119.03
Statutory Authority: 6111.03
Rule Amplifies: 6111.03, 6111.44, 6111.45, 6111.46