"I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."
After the submittal of an application for a solution mining project to the chief, a determination will be made as to the completeness of the application. The applicant will be notified of this completeness. Notification of the application shall be published by the division in the weekly circular in accordance with section 1509.06 of the Revised Code. In addition, a legal notice shall be published by the applicant in a newspaper of general circulation in the area of review in which the proposed project is situated. A copy of the legal notice shall also be delivered to all owners or operators of projects utilizing the same zone or formation. Proof of publication, publication date, and an oath as to the delivery to those entitled to personal notice shall be filed with the division within forty days after the complete application was received by the division. The legal notice shall contain at least the following:
Ohio Admin. Code 1501:9-7-07
Promulgated Under: 119.03
Statutory Authority: 119.03
Rule Amplifies: 1509.221
Prior Effective Dates: 11/26/1982, 04/18/1984 (Emer.), 07/02/1984, 04/15/2004
Rule promulgated under: RC 119.03
Rule authorized by: RC 1509.221
Rule amplifies: RC 1509.221
RC 119.032 review dates: 9/16/03, 1/27/04, 4/15/09