Figure 4
Action | ||||
Site review (Upon receipt of document) | Division review and response to submittal | Applicant/ permittee resubmittal (upon notification of deficiencies from the chief) | Division review and response to resubmittal | |
Procedures | Time | |||
Material modification review | 5 business days | 5 business days | 5 business days | 5 business days |
Approval to commence operations review | 15 business days | 15 business days | 10 business days | 5 business days |
Amendment review | 15 business days | 20 business days | 10 business days | 10 business days |
Ohio Admin. Code 1501:9-4-05
Five Year Review (FYR) Dates: 01/13/2027
Promulgated Under: 119.03
Statutory Authority: 1509.03, 1509.22
Rule Amplifies: 1509.01, 1509.02, 1509.03, 1509.22