For all materials, such as borrow soil, aggregate, riprap stone, and filter material, that are proposed for use in the dam or levee, the applicant shall determine the locations and extents of these materials, and their structural properties and gradations when incorporated into the proposed dam or levee, and show the locations of these materials on the plans.
A construction materials investigation shall be conducted to determine the suitability of the material to construct a dam or levee.
Ohio Admin. Code 1501:21-11-03
Five Year Review (FYR) Dates: 3/3/2028
Promulgated Under: 119.03
Statutory Authority: 1521.06
Rule Amplifies: 1521.06, 1521.061
Prior Effective Dates: 04/15/1972, 10/15/1981, 12/09/1999, 01/16/2005, 05/24/2018