Section 85-02-03-06 - Progress Report1. The grantee shall submit to the director a biannual progress report, prescribed by the energy infrastructure and impact office. The biannual progress report must be received by the energy infrastructure and impact office by the twentieth day of June and December of every year of the project.2. The director may conduct onsite project status visits to review and document utilization of the grant. The director shall provide advance notice to the grantee of any project status visits. The grantee shall provide the director with any project documentation upon request by the director; assist with inspection of equipment purchased, completed construction, or review of any other project expenditures; and provide a description of the remaining budget and timeline for the project.3. If a grantee is delinquent in submitting a progress report or does not comply with the project status visit, the director may delay grant reimbursements.N.D. Admin Code 85-02-03-06
Adopted by Administrative Rules Supplement 371, January 2019, effective 1/1/2019.General Authority: NDCC 28-32-02
Law Implemented: NDCC 57-62-05