The owner shall begin decommissioning within twelve months after abandonment or the end of its useful life. Decommissioning must be completed within twenty-four months after abandonment or the end of its useful life unless the commission approves a plan specifying the steps and schedules to return the facility to operation.
N.D. Admin Code 69-09-09-04
General Authority: NDCC 28-32-02, 49-02-27
Law Implemented: NDCC 49-02-27