Payment = (Qualifying facility's capacity factor) (Projected capacity factor of the facility to be avoided) (Contracted capacity payment price)
"Capacity factor" means the average on peak period metered capacity delivered to the utility for the billing period divided by the greatest fifteen-minute metered capacity delivered for the on peak period of the same billing period.
OBJECTION
THE LEGISLATIVE COUNCIL'S COMMITTEE ON ADMINISTRATIVE RULES OBJECTS TO CHANGES TO NORTH DAKOTA ADMINISTRATIVE CODE SECTION 69-09-07-09 ADOPTED BY THE PUBLIC SERVICE COMMISSION EFFECTIVE MAY 1991 RELATING TO THE RATES THAT ELECTRIC UTILITIES MUST PAY FOR POWER PURCHASED FROM QUALIFYING FACILITIES.
The committee objects to this rule because:
Section 28-32-03.3 provides that after the filing of a committee objection, the burden of persuasion is upon the agency in any action for judicial review or for enforcement of the rule to establish that the whole or portion thereof objected to is within the procedural and substantive authority delegated to the agency. If the agency fails to meet its burden of persuasion, the court shall declare the whole or portion of the rule objected to invalid and judgment shall be rendered against the agency for court costs.
History: Effective August 9, 1991.
General Authority: NDCC 28-32-03.3
N.D. Admin Code 69-09-07-09
General Authority: NDCC 49-02-02
Law Implemented: NDCC 49-02-02