N.D. Admin. Code 33.1-14-07-10

Current through Supplement No. 394, October, 2024
Section 33.1-14-07-10 - Flue connections

Each gas-fired boiler must be equipped with a four inch [10.16 centimeter] vent pipe or flue extended to an approved location outside the building or connected to a chimney flue. If the horizontal run is more than ten feet [3.05 meters], the vent must be increased to six inches [15.24 centimeters]. A draft hood of approved design must be provided on each boiler.

N.D. Admin Code 33.1-14-07-10

Adopted by Administrative Rules Supplement 2020-377, July 2020, effective 7/1/2020.

General Authority: NDCC 23.1-16

Law Implemented: NDCC 23.1-16