N.D. Admin. Code 33.1-14-05-19

Current through Supplement No. 394, October, 2024
Section 33.1-14-05-19 - Fusible plugs
1. Fire-actuated fusible plugs, if used, must conform to the requirements of the American Society of Mechanical Engineers Code for power boilers.
2. They may be replaced by steel plugs if the boiler is gas-fired or oil-fired and is equipped with a low water fuel cutoff.

N.D. Admin Code 33.1-14-05-19

Adopted by Administrative Rules Supplement 2020-377, July 2020, effective 7/1/2020.

General Authority: NDCC 23.1-16

Law Implemented: NDCC 23.1-16