19A N.C. Admin. Code 2D.0825

Current through Register Vol. 39, No. 11, December 2, 2024
Section 02D .0825 - CONFIDENTIALITY OF COST ESTIMATES

All cost estimates prepared by the Department for the purpose of comparing bids shall be confidential and not disclosed until after the opening of bids.

19A N.C. Admin. Code 02D .0825

Authority G.S. 133-33;
Eff. September 1, 1981;
Amended Eff. May 1, 1983;
Recodified from 19A NCAC 02D .0823;
Amended Eff. February 1, 2008; February 1, 1995; October 1, 1993; October 1, 1991;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. September 6, 2016.
Authority G.S. 133-33;
Eff. September 1, 1981;
Amended Eff. May 1, 1983;
Recodified from 19A NCAC 02D .0823;
Amended Eff. February 1, 2008; February 1, 1995; October 1, 1993; October 1, 1991.