Current through Register Vol. 39, No. 11, December 2, 2024
Section 04B .0127 - CERTIFICATE OF PLAN APPROVAL(a) The Commission shall issue a certificate of plan approval to the applicant by hard copy or electronic submittal. Before construction begins, that documentation shall be posted at the primary entrance of the job site or other location that is observable to the public and inspectors.(b) No person may initiate a land-disturbing activity until notifying the approving authority of the date that the land-disturbing activity will begin.15A N.C. Admin. Code 04B .0127
Authority G.S. 113A-54(b);
Temporary Rule Eff. November 1, 1990, for a period of 180 days to expire on April 29, 1991;
ARRC Objection Lodged November 14, 1990;
ARRC Objection Removed December 20, 1990;
Eff. January 1, 1991;
Amended Eff. July 1, 2000;
Readopted Eff. April 1, 2020.Filed as a Temporary Rule Eff. 11/1/1990, for a period of 180 days to expire on April 29, 1991;
Authority G.S. 113A-54(b);
ARRC Objection Lodged November 14, 1990;
ARRC Objection Removed December 20, 1990;
Eff. 1/1/1991;
Amended Eff. 7/1/2000.Readopted by North Carolina Register Volume 34, Issue 21, May 1, 2020 effective 4/1/2020.