15A N.C. Admin. Code 2K.0203

Current through Register Vol. 39, No. 11, December 2, 2024
Section 02K .0203 - PROFESSIONAL ENGINEER REQUIREMENTS

The design, preparation of the plans and specifications, inspection of the construction of or on the dam, and certification that the dam was constructed, repaired, altered, or removed according to the plans approved by the Director and that the dam or its remains are safe shall be done by a legally qualified engineer and shall bear his professional seal unless exempted under the provisions of G.S. 89C-25.

15A N.C. Admin. Code 02K .0203

Authority G.S. 143-215.29,-31;
Eff. June 15, 1980;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. December 23, 2017.
Authority G.S. 143-215.29,-31;
Eff. 6/15/1980.