N.Y. Comp. Codes R. & Regs. Tit. 6 §§ 219-3.9

Current through Register Vol. 46, No. 50, December 11, 2024
Section 219-3.9 - Stack testing
(a) Each facility subject to this Subpart must be tested while burning the normal waste to be incinerated in that facility, to demonstrate compliance with the standards in this Subpart. At a minimum, each incinerator must be tested at startup and annually thereafter for particulates, hydrogen chloride, oxygen and carbon monoxide emissions. Additional testing will be at the discretion of the commissioner.
(b) A test protocol, including the configuration of breeching, stack and test port locations and test methods must be submitted for the commissioner's approval at least 30 days prior to stack testing.
(c) Witnessing of all stack tests by the commissioner's representative is required. Results of any stack test done in the absence of an approved protocol, or which is not witnessed, will not be accepted.
(d) Three copies of the stack test report must be submitted by the permittee to the commissioner within 60 days after completion of the tests, in accordance with section 202.3 of this Title.

N.Y. Comp. Codes R. & Regs. Tit. 6 §§ 219-3.9