Note:The cost of individual items of equipment of small value (for example, $200 or less) or of short life, including small portable tools and implements, shall not be charged to steam plant accounts unless the correctness of the accounting therefor is verified by current inventories. The costs shall be charged to the appropriate operating expense or clearing accounts, according to the use of such items, or, if such items are consumed directly in construction work, the cost shall be included as part of the cost of the construction.
Note:When a part only of a plant or project is placed in operation but the construction work as a whole is incomplete, that part of the cost of the property placed in operation shall be treated as "steam plant in service" and interest thereon as a charge to construction shall cease.
N.Y. Comp. Codes R. & Regs. Tit. 16 § 463.4