Current through Register Vol. 46, No. 45, November 2, 2024
Section 255.1003 - General requirements of a GDPIM plan(a) Unless exempted in subdivision (b) of this section, sections 255.1003 through 255.1015 of this Part prescribe the minimum requirements for a GDPIM program for any gas distribution pipeline covered under this Part, including liquefied petroleum gas systems. A gas distribution operator, other than a master operator or small LPG operator, must follow the requirements in sections 255.1005 through 255.1013 of this Part. A master operator or small LPG operator of a gas distribution pipeline must follow the requirements in section 255.1015 of this Part.(b)Exceptions.Sections 255.1003 through 255.1015 of this Part do not apply to an individual service line directly connected to a transmission, gathering, or production pipeline.
N.Y. Comp. Codes R. & Regs. Tit. 16 § 255.1003