N.Y. Comp. Codes R. & Regs. tit. 16 § 255.150

Current through Register Vol. 46, No. 45, November 2, 2024
Section 255.150 - Passage of internal inspection devices
(a) Except as provided in subdivision (b) of this section, each new transmission line and each pipe section, valve, fitting or other line component of a transmission line that is replaced must be designed and constructed to accommodate the passage of instrumented internal inspection devices.
(b) This section does not apply to:
(1) manifolds;
(2) station piping such as at compressor stations, meter stations, or regulator stations;
(3) piping associated with storage facilities, other than a continuous run of transmission line between a compressor station and storage facilities;
(4) cross-overs;
(5) sizes of pipe for which an instrumented internal inspection device is not commercially available; and
(6) transmission lines, operated in conjunction with a distribution system, which are installed in Class 4 locations.

N.Y. Comp. Codes R. & Regs. Tit. 16 § 255.150