N.Y. Comp. Codes R. & Regs. tit. 16, Appendices, app 7-F

Current through Register Vol. 46, No. 43, October 23, 2024
Appendix 7-F

FORM A

STATE OF NEW YORK

PUBLIC SERVICE COMMISSION

* * *

REPORT OF SPECIFICATIONS OF PROPOSED CONSTRUCTION

of

LIQUID PETROLEUM PIPELINE TO DE SUBJECTED TO PRESSURE

16 NYCRR 258.4 (a)

(Submitted in Triplicate)

* * *

Corporation ____________Date ________

Route: From ____________To ____________

New Construction ____________Reconstruction ____________

Counties traversed ____________

Towns traversed ____________

Cities traversed ____________

Incorporated villages traversed ____________

Estimated date: Start of construction ____________

Completion of construction ____________

Identity of line (corporation name or number) ____________

* * *

Required filing: The following maps, sketches, and drawings shall be filed with and as a part of this report:

(a) Three sets of current U. S. Geological Survey Maps (71/2 or 15-minute) sufficient to show the entire route of the proposed construction or reconstruction and an area of one mile on either side of the route. The route of the construction or reconstruction shall be clearly indicated thereon.
(b) Three sets of strip maps and design drawings showing details of the proposed construction or reconstruction.

* * *

Note: Where more than one construction type design factor is used, the specifications relative to each shall be separately listed. Where necessary, supply the requested information on attached sheets identified by the Roman numeral, number, and letter designation of the item on this form.

* * *

I. General

Length

Nominal outside diameter, "D," inches

Nominal wall thickness, "t," inches

Type and/or grade of pipe

Manufacturer of steel

Manufacturer of pipe

Type of longitudinal joint

Specified minimum yield strength, psig

Nominal ultimate strength, psig

Is pipe new or used

If used pipe is employed, describe the inspection and reconditioning

Mill test pressure, psig

Certified maximum operating pressure, psig

Calculated pipe stress (hoop stress) psig

Where PD = stress

2t

Ratio of pipe stress to yield strength, percent

Check of pipe specifications:

Are the physical and chemical specifications of pipe to be verified by outside laboratories?

By whom?

(a) By location, what percentage of the welds are to be radiographed?

By whom?

II. Fabrication (see 16 NYCRR 258.7)

What inspection procedures will be followed for detection of gouges, grooves, and dents for:

Factory coated pipe

Field coated pipe

III. Railroad, road, and water crossings (see 16 NYCRR 258.5)

Railroad crossings

List, giving location

Indicate whether cased or not; if not cased, provide basis

Road crossings

List, giving location

Indicate whether cased or not

Indicate if heavier wall carrier pipe is used

Lake, river, stream, or creek crossings

List, giving location

Describe any special construction precautions to be followed

Pipeline encroachments

List any encroachments to railroads, by location

List any encroachments to roads, in which special construction precautions will be employed; identify by location

IV. Valves (see 16 NYCRR 258.12)

Manual valves

Number of sectionalizing valves

Spacing of sectionalizing valves

Type, make, and location of any automatic valves to be used

V. Minimum cover and clearance (see 16 NYCRR 258.6)

If minimum prescribed cover and clearance cannot be maintained, indicate location, nature of problem, and cover or clearance to be employed, plus special precautions to be observed.

VI. Corrosion control (see 16 NYCRR 258.10)

Type of field coating:

For pipe (if not factory coated)

For girth welds and fittings

Type of test of coating before backfill

Type of test of coating after backfill

Proposed cathodic protection

Image

N.Y. Comp. Codes R. & Regs. tit. 16, Appendices, app 7-F